Creating Pre-transaltion/Analysis projects with SDL Project Automation API causes max Cals licences error

Hi All,

we have an application that creates automatically new sdl projects with SDL Project Automation API (we changed the code we found on online API documentation according to our needs). The application runs different tasks (analysis-pre-translation and even generate target tanslations when required).

Before January everything was working fine, and the application could create as much as more than 100 projects per hour (under peaks).

After January (we didn't chage anything on application's code) this process "eats" and consumes all CALs available. It seems that now the process reserves a CAL each time it creates a project, and under peaks it fails beacuse of maximum number of CALs reached. 

Before Januay this application had been working that way for over 5 years under all different previous SDL Studio versions (from 2009-2011 to 2015).

We have the very same problem both with dinamic licences or a node licence intalled on the computer where application runs.

Could some one help?

Thanks in advance.

Regards,
Giorgio